We conducted an additional review to assess whether a commercial air leakage test was required. By identifying an alternative compliance route, we helped overcome programme constraints and restricted access to the unit, avoiding the need for additional testing costs.
View more about the scheme on Berkeley’s website here.
An EPC was issued within 48 hours of the initial request without the need for a commercial air leakage test. This saved the client additional costs, avoided delays and ensured compliance requirements were met. We also reviewed the proposal against BREEAM requirements and confirmed that all relevant credits remained unaffected.
A review of the BREEAM requirements confirmed that the proposed approach had no impact
on the credits achieved, ensuring wider sustainability objectives remained intact.